Recovering Lost Time and Materials on a Capital Project in Venezuela

An EPC company was losing time and material on a capital project routed through a single 3PL to a wide supplier base. With C2C®, HAL, Inc. delivered real-time transparency to the whole materials supply chain.

The EPC company’s on-site yard in Venezuela depended on a steady, accurate flow of material from multiple suppliers through a single 3PL in Houston — and neither the flow nor the accuracy could be taken for granted.

  • Project delays resulted from material moving through receiving, packing, and consolidation without consistent visibility, with problems surfacing late.
  • Pilferage and loss rates ran as high as 20% of managed material, with no systematic way to trace where or how items went missing.

HAL, Inc. layered C2C® over the existing 3PL software rather than replacing it, giving every party the same, real-time view of every piece of material.

  • Materials management controls with full ERP integration
  • PO expediting and management, two levels below the line item
  • Receiving, checking, warehousing, packing, and over-packing
  • Multi-site consolidation, deconsolidation, and reconsolidation
  • Seamless data and material exchange between the EPC company and 3PLs